StyleSignal

An internal tool that tracks every style from design to ex-factory, scores its launch risk, and tells merchandising, design and production teams whether to launch, mitigate, delay or drop it, weeks before it becomes a problem.

Product ManagerProduct AnalystProgram ManagerBusiness Operations
89%on-time style launches (up from 71%)
3.5 wksearlier warning on at-risk styles
−40%time spent in status meetings
1shared source of truth across 4 teams
01
The product

From spreadsheets to a decision tool

Teams already had the data: milestone dates in the PLM system, trackers in Excel, updates over email. What they didn't have was one answer to "will this style make it, and if not, what do we do?" StyleSignal gives them that answer.

Track

One readiness view

8 standard milestones for every style, from design approval to ex-factory, each with an owner and a due date.

Score

Launch risk score

A 0–100 score built from how late milestones are, how much work is left versus weeks to launch, and how critical each milestone is.

Decide

Recommended action

Launch, launch with a fix, move to a later wave, or drop, with the reason and the owner who needs to act.

02
Problem & opportunity

Late styles were found too late

On-time launches
71%

of styles hit their launch date before StyleSignal

Late discovery
2 wks

average warning before a missed launch, too late to fix

Manual effort
6 hrs

a week per merchandiser spent chasing and compiling status updates

Baseline from a discovery audit of one season (sample data).

03
Users

Built for the people who make the call

Primary user

Merchandiser

"I find out a style is late when it's already too late to swap it."

Job to be done: protect the launch plan and revenue.

Contributor

Product developer

"I update the same status in three different places."

Job to be done: update a milestone once and move on.

Decision-maker

Director, Planning

"Just tell me what's at risk and what it's worth."

Job to be done: make the call on delays or drops in a 15-minute review.

Discovery: 10 stakeholder interviews, shadowing 2 weekly line reviews, audit of 3 existing trackers (sample).

04
Product requirements

The PRD, in brief

Goals
  • Raise on-time launches from 71% to 85%+
  • Flag at-risk styles at least 4 weeks before launch
  • Cut manual status reporting by 30%+
  • Get 80%+ weekly use by merchandisers
Requirements
  • 8 standard milestones, each with an owner
  • Risk score with a clear explanation (no black box)
  • Recommended action per style, based on demand
  • Filters by collection, category and vendor
Out of scope (v1)
  • Two-way sync with the PLM system (v1 reads a weekly export)
  • Supplier-facing portal
  • Automatic schedule changes
Success metrics
  • On-time launch %, weeks of advance warning
  • Revenue at risk that was recovered
  • Weekly active users, hours saved
US-01As a merchandiser, I want every style's launch risk in one view so I can spend my time on the few that need attention.
US-02As a merchandiser, I want to know why a style is at risk and who owns the fix so I can follow up the same day.
US-03As a planning director, I want revenue at risk by collection so I can decide on delays and drops in one meeting.
05
The MVP · interactive

Try StyleSignal

Pick a style, change a milestone's status or days late, and watch the risk score and recommendation update.

#Milestone · ownerStatusDays late
Launch risk score
—
0 · Low3060100 · High
Recommendation
—
What's driving the score
    MVP hypothesis

    If merchandisers see an explained risk score every week, they'll act on at-risk styles 3+ weeks sooner.

    How we tested it

    Piloted with one collection team for a season, while a second team kept using the Excel trackers. On-time launches were compared at the end.

    Built lean

    The MVP runs on a weekly PLM export with transparent scoring rules. The logic table is in the PRD so anyone can audit it.

    06
    Live season view · interactive

    Fall season readiness

    Styles tracked—
    On track—
    At risk—score 30–59
    Critical—score 60+
    Revenue at risk—
    Avg days late—late milestones only
    —

    Risk by vendor · click a vendor to filter

    On trackAt riskCritical

    Why styles are late · click a cause to filter

    Milestone progress · share of styles complete

    Impact · on-time launch % by season

    Action list · highest risk first

    StyleCollectionVendorLaunch inScoreRecommendationNext action · owner

    All data is illustrative sample data, created for this portfolio.

    07
    Product roadmap

    Now, Next, Later

    Now · v1 (launched)

    Readiness + risk

    • 8 standard milestones with owners
    • Explained risk score and recommended action
    • Season dashboard and action list
    • Weekly PLM export
    Next · v1.1

    Fewer surprises

    • Monday alerts by email and Teams to milestone owners
    • "What if" view: move a style to wave 2 and see the revenue impact
    • Vendor scorecards built on on-time history
    Later · v2

    Connected

    • Daily two-way PLM sync
    • Supplier portal for milestone updates
    • Risk scoring that learns from past seasons
    Gate 1 · M1Problem validated
    Gate 2 · M2PRD and scoring rules approved
    Gate 3 · M4Pilot with 1 team
    Gate 4 · M6Roll out to all teams

    Early in the pilot, the team wanted an AI model to predict delays. I chose simple, explained scoring rules instead. Merchandisers wouldn't act on a score they couldn't question, and trust was the adoption risk. Weekly use reached 86% in the pilot.

    The key product trade-off
    08
    Product artifacts

    The work behind it

    PDF · 53 KBPRD + scoring logicOpen ↗ Excel · 14 KBBusiness caseDownload ↗ PDF · 49 KBRoadmap + rollout planOpen ↗ PDF · 47 KBPilot results readoutOpen ↗